A:
This is not an arbitration clause, but an expert determination clause, and hence the provisions of the Arbitration and Conciliation Act, 1996 would not apply
B:
An interim order under section 9 would be possible depending upon the circumstances.
C:
An interim order will not be possible till the formulation of the decision by the Chief Architect of Architecture Firm
D:
The clause is unenforceable since only an Arbitral Tribunal can determine such a matter and the court will order the setting up of an arbitral tribunal first.
E:
An interim order would be possible but only if consented to by both the parties.
Explanation
A: This is not an arbitration clause, but an expert determination clause, and hence the provisions of the Arbitration and Conciliation Act, 1996 would not apply.
Explanation:
Based on the provided principle and the description of the clause in question, it appears that the clause titled "Arbitration" is not actually an arbitration clause but rather an expert determination clause. In an expert determination clause, the parties agree to refer a dispute to an independent third party with expertise in the relevant subject matter to make a determination. This is different from arbitration, where disputes are resolved through a formal arbitration process.
Since the clause does not contemplate arbitration and instead involves expert determination by the Chief Architect of Architecture Firm D, the provisions of the Arbitration and Conciliation Act, 1996, would not apply. Therefore, the parties would not succeed in seeking an interim order under section 9 of the Act in this case.
Options B, C, D, and E are not applicable because they assume that the clause is an arbitration clause, which is not the case based on the provided information.